2.1.6 Construction Planning: Recommend for purchase and expedite the procurement of long-lead items to ensure their delivery by the required dates.
2.1.5.1 Make recommendations to the Owner and the Architect/Engineer regarding the division of Work in the Drawings and Specifications to facilitate the bidding and awarding of Trade Contracts, allowing for phased construction taking into con- sideration such factors as time of performance, availability of labor, overlapping trade jurisdictions, and provisions for tem- porary facilities.
2.1.5.2 Review the Drawings and Specifications with the Architect/Engineer to eliminate areas of conflict and overlapping in the Work to be performed by the various Trade Contractors and prepare prequalification criteria for bidders.
2.1.5.3 Develop Trade Contractor interest in the Project and as working Drawings and Specifications are completed, take competitive bids on the Work of the various Trade Contractors. After analyzing the bids, either award contracts or recom mend to the Owner that such contracts be awarded.
2.1.6 Equal Employment Opportunity: Determine applicable requirements for equal emloyment opportunity programs for in- clusion in Project bidding documents.
2.2 Construction Phase
AMBLE
2.2.1 Project Control: Monitor the Work of the Trade Contractors and coordinate the Work with the activities and respon- sibilities of the Owner, Architect/Engineer and Construction Manager to complete the Project in accordance with the Owner's objectives of cost, time and quality.
2.2.1.1 Maintain a competent full-time staff at the Project site to coordinate and provide general direction of the Work and progress of the Trade Contractors on the Projec
2.2.1.2 Establish on-site organization and lines authority in order to carry out the overall plans of the Construction Team.
2.2.1.3 Establish procedures for coordination among the Owner, Architect/Engineer, Trade Contractors and Construction Manager with respect to all aspects of the Project and implement such procedures.
2.2.1.4 Schedule and conduct progress meetings at which Trade Contractors, Owner, Architect/Engineer and Construction Manager can discuss jointly such matters as procedures, progress, problems and scheduling.
2.2.1.5 Provide regular monitoring of the schedule as construction progresses. Identify potential variances between schedul ed and probable completion dates. Review schedule for Work not started or incomplete and recommend to the Owner and Trade Contractors adjustments in the schedule to meet the probable completion date. Provide summary reports of each monitoring and document all changes in schedule.
2.2.1.6 Determine the adequacy of the Trade Contractors' personnel and equipment and the availability of materials and sup- plies to meet the schedule. Recommend courses of action to the Owner when requirements of a Trade Contract are not being met.
2.2.2 Physical Construction: Provide all supervision, labor, materials, construction equipment, tools and subcontract items which are necessary for the completion of the Project which are not provided by either the Trade Contractors or the Owner. To the extent that the Construction Manager performs any Work with his own forces, he shall, with respect to such Work, per- form in accordance with the Plans and Specifications and in accordance with the procedure applicable to the Project.
2.2.3 Cost Control: Develop and monitor an effective system of Project cost control. Revise and refine the initially approved Project Construction Budget, incorporate approved changes as they occur, and develop cash flow reports and forecasts as needed. Identify variances between actual and budgeted or estimated costs and advise Owner and Architect/Engineer whenever projected cost exceeds budgets or estimates.
إدارة التشييد المتخصصة
AGC DOCUMENT NO. 500 OWNER CONSTRUCTION MANAGER AGREEMENT JULY 1980